Construction site of the Nantong-Suzhou-Jiaxing-Ningbo High-Speed Railway.
Recently, at the construction site of the Nantong-Suzhou-Jiaxing-Ningbo High-Speed Railway, the first precast concrete box girder, measuring 32.6 meters in length and weighing 697 tons, was successfully installed on the mainline bridge pier. This milestone marks the full transition of the Zhejiang section of the railway into the girder erection phase and paves the way for subsequent large-scale girder installation.
Earlier, on September 7, at the Cixi Beam Prefabrication Yard on the southern shore of Hangzhou Bay, two 550-t
on beam lifters operated simultaneously to hoist a 40.6-meter-long, 980-ton simply supported double-track box girder onto the Cixi Grand Bridge. This achievement signifies the completion of the first box girder installation in the Ningbo section of the railway, officially commencing the girder erection work. With both sides of Hangzhou Bay entering this new construction phase, the project is accelerating toward its scheduled completion in 2027 as part of the national "Eight Vertical and Eight Horizontal" high-speed rail network's coastal corridor.
According to relevant sources, following the commencement of girder erection on the land sections on both sides of the bay, the installation of the first sea-based girder for the Hangzhou Bay Cross-Sea Railway Bridge is also set to begin in the near future.
The Nantong-Suzhou-Jiaxing-Ningbo High-Speed Railway is a crucial component of the coastal corridor of China's "Eight Vertical and Eight Horizontal" high-speed rail network. Starting from Nantong West Station on the Yancheng-Nantong High-Speed Railway, it runs south through Suzhou in Jiangsu Province, and Jiaxing and Ningbo in Zhejiang Province, eventually connecting to Ningbo Station at the Ningbo hub. The new line spans 301 kilometers, designed for a speed of 350 km/h, and includes 11 stations. The construction period is set at five years.
Upon completion, this high-speed railway will link with several other lines, including the Yancheng-Nantong High-Speed Railway, the Shanghai-Nanjing Yangtze River High-Speed Railway, the Shanghai-Kunming High-Speed Railway, and the Ningbo-Taizhou-Wenzhou Railway. It will allow passengers from Ningbo to reach Shanghai in approximately one hour without detouring through Hangzhou, officially integrating Shanghai and Ningbo into a "one-hour transportation circle" and fully opening up the northbound high-speed rail corridor from Ningbo